Product, capacity and operating basis
Stored product, design liquid level, operating temperature, density, corrosion allowance, filling and withdrawal rates, design pressure or vacuum and required service life establish the design basis.
CangZhou Simei EnergyOil terminal · API 650 storage tanks
Simei Energy coordinates engineering, fabrication, export supply and field erection of welded aboveground tanks for crude oil, gasoline, diesel, jet fuel and other petroleum products in Africa and the Middle East.

API 650 tank definition
Tank capacity alone is not enough. Product properties, operating limits, site loads, roof type, corrosion strategy, nozzles and inspection requirements must be fixed in one approved tank data sheet.
Stored product, design liquid level, operating temperature, density, corrosion allowance, filling and withdrawal rates, design pressure or vacuum and required service life establish the design basis.
Fixed-roof, internal-floating-roof and external-floating-roof arrangements are evaluated against product volatility, emissions requirements, rainfall, wind, maintenance and the owner’s operating philosophy.
Tank diameter and height, shell-course thicknesses, bottom and annular plates, roof structure, wind girders, anchorage and settlement criteria are coordinated with applicable loads and site conditions.
Plate grades, impact requirements, corrosion allowance, bottom-side protection, internal lining, external coating and cathodic-protection interfaces are selected for the product and environment.
Inlets, outlets, drains, vents, manways, stairs, platforms, sampling, automatic tank gauging, temperature measurement and independent overfill protection are arranged for safe operation and maintenance.
Tank reactions, anchor loads and settlement limits are issued for civil design, while piping flexibility, bund layout, drainage, fire protection, lightning and static interfaces are checked with the wider tank farm.
01
The package may include the API 650 data sheet, design calculations, general arrangement, foundation loads, shell-development and fabrication drawings, nozzle schedule, roof and platform drawings, material take-off or BOM, welding requirements, inspection and test plan, and installation procedures.
02
Steel identity and certificates, cutting, edge preparation, rolling, fit-up, welding qualifications, dimensional checks and non-destructive examination are controlled through approved procedures. Inspection hold points and third-party witness requirements are agreed before manufacture.
03
Plates, structural members, nozzles, manways and accessories are identified and packed for shipment. Site erection may use an agreed jacking or conventional sequence, with construction equipment, local labour and supervision boundaries clearly defined in the proposal.
04
Bottom-weld testing, weld examination, dimensional checks, hydrostatic testing when specified, settlement monitoring, coating inspection and final documentation are completed against the approved inspection plan before turnover.
Google & AI search answers
It is a welded aboveground storage tank designed and constructed to the contractually agreed edition of API Standard 650, Welded Tanks for Oil Storage, together with project specifications and local regulations.
Typical applications include crude oil, gasoline, diesel, jet fuel, kerosene and other compatible petroleum products. Product properties and operating conditions must be confirmed before material and roof selection.
Provide the product, net and nominal capacity, preferred diameter or height limits, roof type if known, design temperature, site location, wind and seismic data, corrosion or coating requirements, nozzle list and required delivery scope.
Internal or external floating roofs may be considered for volatile products or emissions control, subject to local regulation, product behaviour, climate, inspection and maintenance requirements. The final choice follows the approved design basis.
Material traceability, welding procedure and welder qualification review, dimensional inspection, radiographic, ultrasonic, magnetic-particle or liquid-penetrant examination as applicable, bottom-weld testing, hydrostatic testing and coating inspection can be specified.
Yes, according to the agreed contract boundary. Simei can coordinate engineering, fabricated components, export packing, site supervision or erection and testing. Local labour, cranes, civil foundations and utilities are identified separately when not included.
No. Simei Energy provides technical services, equipment supply and engineering or EPC delivery. We do not provide investment, financing, EPC+F, BOOT, lease-to-own or deferred-payment funding.
API 650 storage tanks
Send the product, capacity, site country, roof preference, design conditions and required supply or erection boundary.